Experience example
"My room isn't dirty, I just have everything on display" - Every Teenager Ever
Industry
Utilities
Sector
Water & Sewerage
Segment
Sewage
Project
The client is a water and sewerage utility responsible for managing over $2bn worth of assets. They had identified that one of their key metropolitan sewage pump stations was the subject of numerous odour complaints. On investigation it was identified that there was a presence of Hydrogen Sulfide causing the odour and the electrical systems at the site had also reached end of life. The client then initiated a project to:
Cromarty were engaged by the principal contractor to provide all electrical and automation services.
Solution
Cromarty worked collaboratively with the client and the principal contractor to design and deliver the following:
Outcome
Due to the criticality of the site the changeover needed to take place in one day. During the changeover, the pumps ran off a generator with a temporary control system installed. The legacy MCC was disconnected and removed and the new one put into position and then recommissioned. The client was delighted as the works commenced at 8am and the site was returned to full automatic operation and SCADA monitoring by 8pm the same day without any environmental issues or service interruptions.
Subsequently the odour control system has resulted in a significant reduction of odour complaints, it now has enhanced Hydrogen Sulfide monitoring and alarming, it also has a state of the art control system and an emergency power supply to keep the site operational, all in all a great environmental and operational result.